1.修改工况配置,适应新旧工况
This commit is contained in:
@@ -5,91 +5,16 @@ import copy
|
||||
# 注意:根据实际项目路径调整导入,若本地测试可注释掉
|
||||
from ..core.logging_config import get_logger
|
||||
import json
|
||||
|
||||
from .operating_mode_config import BASE_PERIODS
|
||||
|
||||
logger = get_logger(__name__)
|
||||
|
||||
|
||||
class ConstructionMonitorUtils:
|
||||
def __init__(self):
|
||||
# 原始工况周期映射表(保持不变)
|
||||
self.base_periods = {
|
||||
"路基或预压土填筑,连续填筑":1,
|
||||
"路基或预压土填筑,两次填筑间隔时间较长":7,
|
||||
"预压土或路基填筑完成,第1~3个月":7,
|
||||
"预压土或路基填筑完成,第4~6个月":14,
|
||||
"仰拱(底板)施工完成后,第1个月": 7,
|
||||
"预压土或路基填筑完成,6个月以后":30,
|
||||
"仰拱(底板)施工完成后,第2至3个月": 14,
|
||||
"仰拱(底板)施工完成后,3个月以后": 30,
|
||||
"仰拱(底板)施工完成后,第1个月": 7, # 原:仰拱(底板)施工完成后,第1个月
|
||||
"仰拱(底板)施工完成后,第2至3个月": 14, # 原:仰拱(底板)施工完成后,第2至3个月
|
||||
"仰拱(底板)施工完成后,3个月以后": 30, # 原:仰拱(底板)施工完成后,3个月以后
|
||||
"无砟轨道铺设后,第1至3个月": 30, # 原:无砟轨道铺设后,第1至3个月
|
||||
"无砟轨道铺设后,4至12个月": 90, # 原:无砟轨道铺设后,4至12个月
|
||||
"无砟轨道铺设后,12个月以后": 180, # 原:无砟轨道铺设后,12个月以后
|
||||
"墩台施工到一定高度": 30, # 无格式差异,保留原样
|
||||
"墩台混凝土施工": 30, # 无格式差异,保留原样
|
||||
"预制梁桥,架梁前": 30, # 原:预制梁桥,架梁前
|
||||
"预制梁桥,预制梁架设前": 1, # 原:预制梁桥,预制梁架设前
|
||||
"预制梁桥,预制梁架设后": 7, # 原:预制梁桥,预制梁架设后
|
||||
"桥位施工桥梁,制梁前": 30, # 原:桥位施工桥梁,制梁前
|
||||
"桥位施工桥梁,上部结构施工中": 1, # 原:桥位施工桥梁,上部结构施工中
|
||||
# "架桥机(运梁车)通过": 7, # 无格式差异,保留原样
|
||||
"桥梁主体工程完工后,第1至3个月": 7, # 原:桥梁主体工程完工后,第1至3个月
|
||||
"桥梁主体工程完工后,第4至6个月": 14, # 原:桥梁主体工程完工后,第4至6个月
|
||||
"桥梁主体工程完工后,6个月以后": 30, # 原:桥梁主体工程完工后,6个月以后 ''
|
||||
"轨道铺设期间,前": 30,
|
||||
"轨道铺设期间,后": 14,
|
||||
"轨道铺设完成后,第1个月": 14,
|
||||
"轨道铺设完成后,2至3个月": 30,
|
||||
"轨道铺设完成后,4至12个月": 90,
|
||||
"轨道铺设完成后,12个月以后": 180,
|
||||
"铺路或堆载,一般情况": 1,
|
||||
"填筑或堆载,一般情况": 1,
|
||||
"铺路或堆载,沉降量突变情况": 1,
|
||||
"填筑或堆载,两次填筑间隔时间较长情况":3,
|
||||
"铺路或堆载,两次铺路间隔时间较长情况": 3,
|
||||
"堆载预压或路基填筑完成,第1至3个月":7, # 原:堆载预压或路基铺路完成,第1至3个月
|
||||
"堆载预压或路基填筑完成,第4至6个月": 14, # 原:堆载预压或路基铺路完成,第4至6个月
|
||||
"堆载预压或路基填筑完成,6个月以后": 30, # 原:堆载预压或路基铺路完成,6个月以后
|
||||
"架桥机(运梁车) 首次通过前": 1, # 原:架桥机(运梁车)首次通过前(仅加空格)
|
||||
"架桥机(运梁车) 首次通过后,前3天": 1, # 原:架桥机(运梁车)首次通过后,前3天
|
||||
"架桥机(运梁车) 首次通过后": 7, # 原:架桥机(运梁车)首次通过后(仅加空格)
|
||||
"轨道板(道床)铺设后,第1个月": 14, # 原:轨道板(道床)铺设后,第1个月
|
||||
"轨道板(道床)铺设后,第2至3个月": 30, # 原:轨道板(道床)铺设后,第2至3个月
|
||||
"轨道板(道床)铺设后,3个月以后": 90,
|
||||
"架桥机(运梁车)首次通过前": 1,
|
||||
"架桥机(运梁车)首次通过后,前3天": 1,
|
||||
"架桥机(运梁车)首次通过后": 7,
|
||||
"轨道板铺设前": 14,
|
||||
"轨道板(道床)铺设后,第1至3个月": 14,
|
||||
"轨道板(道床)铺设后,第4至6个月": 30,
|
||||
"轨道板(道床)铺设后,6个月以后": 90,
|
||||
"站场填方路基段填筑完成至静态验收": 14,
|
||||
"桥墩(台)地面处拆模后": 30,
|
||||
"敦身混凝土施工": 30,
|
||||
# "预制梁桥,架梁前": 30,
|
||||
# "预制梁桥,预制梁架设前": 1,
|
||||
"预制梁桥预制梁架设后": 7,
|
||||
"现浇梁,浇筑前": 30,
|
||||
"现浇梁上部结构施工中": 1,
|
||||
"架桥机(运梁车)通过": 2,
|
||||
"桥梁主体工程完工后,第1至3个月": 7,
|
||||
# "桥梁主体工程完工后,第4至6个月": 14,
|
||||
"侨梁主体工程完工后,6个月以后": 30,
|
||||
"轨道铺设,前": 30,
|
||||
"轨道铺设,后": 14,
|
||||
# "轨道铺设完成后,第1个月": 14,
|
||||
# "轨道铺设完成后,2至3个月": 30,
|
||||
# "轨道铺设完成后,4至12个月": 90,
|
||||
# "轨道铺设完成后,12个月以后": 180,
|
||||
# "仰拱(底板)施工完成后,第1个月": 7,
|
||||
# "仰拱(底板)施工完成后,第2至3个月": 14,
|
||||
# "仰拱(底板)施工完成后,3个月以后": 30,
|
||||
# "轨道板铺设前": 14,
|
||||
# "无砟轨道铺设后,第1至3个月": 30,
|
||||
# "无砟轨道铺设后,4至12个月": 90,
|
||||
# "无砟轨道铺设后,12个月以后": 180,
|
||||
"特殊地段隧道施工完成后至静态验收": 14
|
||||
}
|
||||
# 使用公共配置的工况周期映射表
|
||||
self.base_periods = BASE_PERIODS.copy()
|
||||
# 构建中英文括号+逗号兼容映射表
|
||||
self.compatible_periods = self._build_compatible_brackets_map()
|
||||
|
||||
|
||||
@@ -1,5 +1,14 @@
|
||||
from datetime import datetime, date
|
||||
|
||||
from .operating_mode_config import (
|
||||
BASE_PERIODS,
|
||||
OLD_TO_NEW_MAP,
|
||||
CONDITION_GROUP,
|
||||
TRANSITION_RULES,
|
||||
WINTER_BREAK_LABELS,
|
||||
)
|
||||
|
||||
|
||||
class OperatingModePredictor:
|
||||
"""
|
||||
工况预测类(处理二维倒序数据,返回一维列表,仅保留各内嵌列表最新记录)
|
||||
@@ -16,15 +25,15 @@ class OperatingModePredictor:
|
||||
def __init__(self):
|
||||
"""初始化类,加载核心配置"""
|
||||
# 1. 基础工况配置(最终返回的规范名称,含所有新旧工况)
|
||||
self.base_periods = self._load_base_periods()
|
||||
self.base_periods = BASE_PERIODS.copy()
|
||||
# 2. 旧→新等效映射(优先返回新工况)
|
||||
self.old_to_new_map = self._load_old_to_new_map()
|
||||
self.old_to_new_map = OLD_TO_NEW_MAP.copy()
|
||||
# 3. 工况分组(同义工况归为同一分组,复用切换规则)
|
||||
self.condition_group = self._load_condition_group()
|
||||
self.condition_group = CONDITION_GROUP.copy()
|
||||
# 4. 切换触发规则(沿用原逻辑,触发天数+目标工况)
|
||||
self.transition_rules = self._load_transition_rules()
|
||||
self.transition_rules = TRANSITION_RULES.copy()
|
||||
# 5. 冬休标识
|
||||
self.winter_break_labels = {"冬休"}
|
||||
self.winter_break_labels = WINTER_BREAK_LABELS.copy()
|
||||
|
||||
# 辅助映射:标准化名称→base_periods中的规范名称(用于最终返回)
|
||||
self.std_to_canonical = {
|
||||
@@ -55,196 +64,6 @@ class OperatingModePredictor:
|
||||
std_name = std_name.replace(old, new)
|
||||
return std_name
|
||||
|
||||
def _load_base_periods(self):
|
||||
"""加载基础工况配置(最终返回的规范名称,无多余数字)"""
|
||||
return {
|
||||
# 路基工况(新工况优先)
|
||||
"路基或预压土填筑,连续填筑": 1,
|
||||
"路基或预压土填筑,两次填筑间隔时间较长": 7,
|
||||
"预压土或路基填筑完成,第1~3个月": 7,
|
||||
"预压土或路基填筑完成,第4~6个月": 14,
|
||||
"预压土或路基填筑完成,6个月以后": 30,
|
||||
"架桥机(运梁车)首次通过前": 1,
|
||||
"架桥机(运梁车)首次通过后,前3天": 1,
|
||||
"架桥机(运梁车)首次通过后": 7,
|
||||
"轨道板(道床)铺设后,第1至3个月": 14,
|
||||
"轨道板(道床)铺设后,第4至6个月": 30,
|
||||
"轨道板(道床)铺设后,6个月以后": 90,
|
||||
|
||||
# 路基旧工况(保留,无等效则返回)
|
||||
"填筑或堆载,一般情况": 1,
|
||||
"填筑或堆载,两次填筑间隔时间较长情况": 7,
|
||||
"堆载预压或路基填筑完成,6个月以后": 30,
|
||||
"轨道板(道床)铺设后,第1个月": 14,
|
||||
"轨道板(道床)铺设后,第2至3个月": 30,
|
||||
"轨道板(道床)铺设后,3个月以后": 90,
|
||||
|
||||
# 桥梁工况(新工况优先)
|
||||
"桥墩(台)地面处拆模后": 30,
|
||||
"敦身混凝土施工": 30,
|
||||
"预制梁桥,预制梁架设前": 1,
|
||||
"预制梁桥,预制梁架设后": 7,
|
||||
"现浇梁,浇筑前": 30,
|
||||
"现浇梁上部结构施工中": 1,
|
||||
"架桥机(运梁车)通过": 2,
|
||||
"桥梁主体工程完工后,第1至3个月": 7,
|
||||
"桥梁主体工程完工后,第4至6个月": 14,
|
||||
"桥梁主体工程完工后,6个月以后": 30,
|
||||
"轨道铺设,前": 30,
|
||||
"轨道铺设,后": 14,
|
||||
"轨道铺设完成后,第1个月": 14,
|
||||
"轨道铺设完成后,2至3个月": 30,
|
||||
"轨道铺设完成后,4至12个月": 90,
|
||||
"轨道铺设完成后,12个月以后": 180,
|
||||
|
||||
# 桥梁旧工况(保留,无等效则返回)
|
||||
"墩台施工到一定高度": 30,
|
||||
"墩台混凝土施工": 30,
|
||||
"预制梁桥,架梁前": 30,
|
||||
"桥位施工桥梁,制梁前": 30,
|
||||
"桥位施工桥梁,上部结构施工中": 1,
|
||||
"桥梁主体工程完工后,第1至3个月": 7,
|
||||
"轨道铺设期间,前": 30,
|
||||
"轨道铺设期间,后": 14,
|
||||
|
||||
# 隧道工况
|
||||
"仰拱(底板)施工完成后,第1个月": 7,
|
||||
"仰拱(底板)施工完成后,第2至3个月": 14,
|
||||
"仰拱(底板)施工完成后,3个月以后": 30,
|
||||
"无砟轨道铺设后,第1至3个月": 30,
|
||||
"无砟轨道铺设后,4至12个月": 90,
|
||||
"无砟轨道铺设后,12个月以后": 180,
|
||||
|
||||
# 特殊工况
|
||||
"冬休": 0
|
||||
}
|
||||
|
||||
def _load_old_to_new_map(self):
|
||||
"""加载旧→新等效映射(优先返回新工况)"""
|
||||
return {
|
||||
# 路基等效
|
||||
"填筑或堆载,一般情况": "路基或预压土填筑,连续填筑",
|
||||
"填筑或堆载,两次填筑间隔时间较长情况": "路基或预压土填筑,两次填筑间隔时间较长",
|
||||
"预压土或路基填筑完成。第1~3个月": "预压土或路基填筑完成,第1~3个月",
|
||||
"堆载预压或路基填筑完成,6个月以后": "预压土或路基填筑完成,6个月以后",
|
||||
"轨道板(道床)铺设后,第1个月": "轨道板(道床)铺设后,第1至3个月",
|
||||
"轨道板(道床)铺设后,第2至3个月": "轨道板(道床)铺设后,第4至6个月",
|
||||
"轨道板(道床)铺设后,3个月以后": "轨道板(道床)铺设后,6个月以后",
|
||||
|
||||
# 桥梁等效
|
||||
"墩台施工到一定高度": "桥墩(台)地面处拆模后",
|
||||
"墩台混凝土施工": "敦身混凝土施工",
|
||||
"桥位施工桥梁,制梁前": "现浇梁,浇筑前",
|
||||
"桥位施工桥梁,上部结构施工中": "现浇梁上部结构施工中",
|
||||
"桥梁主体工程完工后,第1至3个月": "桥梁主体工程完工后,第1至3个月",
|
||||
"轨道铺设期间,前": "轨道铺设,前",
|
||||
"轨道铺设期间,后": "轨道铺设,后"
|
||||
}
|
||||
|
||||
def _load_condition_group(self):
|
||||
"""加载工况分组(同义工况归为同一分组)"""
|
||||
group_map = {
|
||||
# 路基分组
|
||||
"路基或预压土填筑,连续填筑": "DZ_CONTINUE",
|
||||
"路基或预压土填筑,两次填筑间隔时间较长": "DZ_INTERVAL",
|
||||
"预压土或路基填筑完成,第1~3个月": "DZ_FINISH_1_3",
|
||||
"预压土或路基填筑完成,第4~6个月": "DZ_FINISH_4_6",
|
||||
"预压土或路基填筑完成,6个月以后": "DZ_FINISH_AFTER_6",
|
||||
"架桥机(运梁车)首次通过前": "JQJ_FIRST_BEFORE",
|
||||
"架桥机(运梁车)首次通过后,前3天": "JQJ_FIRST_AFTER_3D",
|
||||
"架桥机(运梁车)首次通过后": "JQJ_FIRST_AFTER",
|
||||
"轨道板(道床)铺设后,第1至3个月": "GDB_FINISH_1_3",
|
||||
"轨道板(道床)铺设后,第4至6个月": "GDB_FINISH_4_6",
|
||||
"轨道板(道床)铺设后,6个月以后": "GDB_FINISH_AFTER_6",
|
||||
|
||||
# 路基旧工况分组(复用新工况分组)
|
||||
"填筑或堆载,一般情况": "DZ_CONTINUE",
|
||||
"填筑或堆载,两次填筑间隔时间较长情况": "DZ_INTERVAL",
|
||||
"堆载预压或路基填筑完成,6个月以后": "DZ_FINISH_AFTER_6",
|
||||
"轨道板(道床)铺设后,第1个月": "GDB_FINISH_1_3",
|
||||
"轨道板(道床)铺设后,第2至3个月": "GDB_FINISH_4_6",
|
||||
"轨道板(道床)铺设后,3个月以后": "GDB_FINISH_AFTER_6",
|
||||
|
||||
# 桥梁分组
|
||||
"桥墩(台)地面处拆模后": "STATIC",
|
||||
"敦身混凝土施工": "STATIC",
|
||||
"预制梁桥,架梁前": "STATIC",
|
||||
"预制梁桥,预制梁架设前": "YZLQ_BEFORE_JS",
|
||||
"预制梁桥,预制梁架设后": "YZLQ_AFTER_JS",
|
||||
"现浇梁,浇筑前": "STATIC",
|
||||
"现浇梁上部结构施工中": "STATIC",
|
||||
"架桥机(运梁车)通过": "STATIC",
|
||||
"桥梁主体工程完工后,第1至3个月": "QL_ZHUTI_1_3",
|
||||
"桥梁主体工程完工后,第4至6个月": "QL_ZHUTI_4_6",
|
||||
"桥梁主体工程完工后,6个月以后": "QL_ZHUTI_AFTER_6",
|
||||
"轨道铺设,前": "STATIC",
|
||||
"轨道铺设,后": "STATIC",
|
||||
"轨道铺设完成后,第1个月": "GD_FINISH_1",
|
||||
"轨道铺设完成后,2至3个月": "GD_FINISH_2_3",
|
||||
"轨道铺设完成后,4至12个月": "GD_FINISH_4_12",
|
||||
"轨道铺设完成后,12个月以后": "GD_FINISH_AFTER_12",
|
||||
|
||||
# 桥梁旧工况分组(复用新工况分组)
|
||||
"墩台施工到一定高度": "STATIC",
|
||||
"墩台混凝土施工": "STATIC",
|
||||
"桥位施工桥梁,制梁前": "STATIC",
|
||||
"桥位施工桥梁,上部结构施工中": "STATIC",
|
||||
"桥梁主体工程完工后,第1至3个月": "QL_ZHUTI_1_3",
|
||||
"轨道铺设期间,前": "STATIC",
|
||||
"轨道铺设期间,后": "STATIC",
|
||||
|
||||
# 隧道分组
|
||||
"仰拱(底板)施工完成后,第1个月": "YG_DIBAN_1",
|
||||
"仰拱(底板)施工完成后,第2至3个月": "YG_DIBAN_2_3",
|
||||
"仰拱(底板)施工完成后,3个月以后": "YG_DIBAN_AFTER_3",
|
||||
"无砟轨道铺设后,第1至3个月": "WZGD_1_3",
|
||||
"无砟轨道铺设后,4至12个月": "WZGD_4_12",
|
||||
"无砟轨道铺设后,12个月以后": "WZGD_AFTER_12",
|
||||
|
||||
# 特殊工况
|
||||
"冬休": "STATIC"
|
||||
}
|
||||
return group_map
|
||||
|
||||
def _load_transition_rules(self):
|
||||
"""加载切换触发规则(沿用原逻辑,以base_periods为准)"""
|
||||
return {
|
||||
# 路基切换规则
|
||||
"DZ_FINISH_1_3": {"trigger_days": 90, "next": ["预压土或路基填筑完成,第4~6个月"]},
|
||||
"DZ_FINISH_4_6": {"trigger_days": 90, "next": ["预压土或路基填筑完成,6个月以后"]},
|
||||
"DZ_FINISH_AFTER_6": {"trigger_days": None, "next": None},
|
||||
"JQJ_FIRST_BEFORE": {"trigger_days": 1, "next": ["架桥机(运梁车)首次通过后,前3天"]},
|
||||
"JQJ_FIRST_AFTER_3D": {"trigger_days": 3, "next": ["架桥机(运梁车)首次通过后"]},
|
||||
"JQJ_FIRST_AFTER": {"trigger_days": None, "next": None},
|
||||
"GDB_FINISH_1_3": {"trigger_days": 30, "next": ["轨道板(道床)铺设后,第4至6个月"]},
|
||||
"GDB_FINISH_4_6": {"trigger_days": 30, "next": ["轨道板(道床)铺设后,6个月以后"]},
|
||||
"GDB_FINISH_AFTER_6": {"trigger_days": None, "next": None},
|
||||
|
||||
# 桥梁切换规则
|
||||
"YZLQ_BEFORE_JS": {"trigger_days": 1, "next": ["架桥机(运梁车)通过"]},
|
||||
"YZLQ_AFTER_JS": {"trigger_days": 7, "next": ["桥梁主体工程完工后,第1至3个月"]},
|
||||
"QL_ZHUTI_1_3": {"trigger_days": 90, "next": ["桥梁主体工程完工后,第4至6个月"]},
|
||||
"QL_ZHUTI_4_6": {"trigger_days": 90, "next": ["桥梁主体工程完工后,6个月以后"]},
|
||||
"QL_ZHUTI_AFTER_6": {"trigger_days": None, "next": None},
|
||||
"GD_FINISH_1": {"trigger_days": 30, "next": ["轨道铺设完成后,2至3个月"]},
|
||||
"GD_FINISH_2_3": {"trigger_days": 60, "next": ["轨道铺设完成后,4至12个月"]},
|
||||
"GD_FINISH_4_12": {"trigger_days": 240, "next": ["轨道铺设完成后,12个月以后"]},
|
||||
"GD_FINISH_AFTER_12": {"trigger_days": None, "next": None},
|
||||
|
||||
# 隧道切换规则
|
||||
"YG_DIBAN_1": {"trigger_days": 30, "next": ["仰拱(底板)施工完成后,第2至3个月"]},
|
||||
"YG_DIBAN_2_3": {"trigger_days": 60, "next": ["仰拱(底板)施工完成后,3个月以后"]},
|
||||
"YG_DIBAN_AFTER_3": {"trigger_days": None, "next": None},
|
||||
"WZGD_1_3": {"trigger_days": 90, "next": ["无砟轨道铺设后,4至12个月"]},
|
||||
"WZGD_4_12": {"trigger_days": 240, "next": ["无砟轨道铺设后,12个月以后"]},
|
||||
"WZGD_AFTER_12": {"trigger_days": None, "next": None},
|
||||
|
||||
# 静态分组(无切换)
|
||||
"DZ_CONTINUE": {"trigger_days": None, "next": None},
|
||||
"DZ_INTERVAL": {"trigger_days": None, "next": None},
|
||||
"STATIC": {"trigger_days": None, "next": None}
|
||||
}
|
||||
|
||||
def _parse_to_date(self, time_str):
|
||||
"""解析时间字符串为date对象(仅保留年月日)"""
|
||||
if not time_str:
|
||||
|
||||
246
app/utils/operating_mode_config.py
Normal file
246
app/utils/operating_mode_config.py
Normal file
@@ -0,0 +1,246 @@
|
||||
# -*- coding: utf-8 -*-
|
||||
"""
|
||||
工况公共配置模块
|
||||
供 get_operating_mode.py(工况预测)和 construction_monitor.py(施工监测)共用
|
||||
"""
|
||||
|
||||
# ==================== 基础工况周期(天) ====================
|
||||
# 含新旧工况及兼容变体,键为工况名称,值为测量间隔天数
|
||||
BASE_PERIODS = {
|
||||
# 路基工况(新工况)
|
||||
"路基或预压土填筑,连续填筑": 1,
|
||||
"路基或预压土填筑,两次填筑间隔时间较长": 7,
|
||||
"预压土或路基填筑完成,第1~3个月": 7,
|
||||
"预压土或路基填筑完成,第4~6个月": 14,
|
||||
"预压土或路基填筑完成,6个月以后": 30,
|
||||
"架桥机(运梁车)首次通过前": 1,
|
||||
"架桥机(运梁车)首次通过后,前3天": 1,
|
||||
"架桥机(运梁车)首次通过后": 7,
|
||||
"轨道板(道床)铺设后,第1至3个月": 14,
|
||||
"轨道板(道床)铺设后,第4至6个月": 30,
|
||||
"轨道板(道床)铺设后,6个月以后": 90,
|
||||
|
||||
# 路基旧工况
|
||||
"填筑或堆载,一般情况": 1,
|
||||
"填筑或堆载,两次填筑间隔时间较长情况": 7,
|
||||
"堆载预压或路基填筑完成,第1至3个月": 7,
|
||||
"堆载预压或路基填筑完成,第4至6个月": 14,
|
||||
"堆载预压或路基填筑完成,6个月以后": 30,
|
||||
"轨道板(道床)铺设后,第1个月": 14,
|
||||
"轨道板(道床)铺设后,第2至3个月": 30,
|
||||
"轨道板(道床)铺设后,3个月以后": 90,
|
||||
|
||||
# 路基兼容变体(铺路/填筑同义)
|
||||
"铺路或堆载,一般情况": 1,
|
||||
"铺路或堆载,沉降量突变情况": 1,
|
||||
"铺路或堆载,两次铺路间隔时间较长情况": 3,
|
||||
|
||||
# 桥梁工况(新工况)
|
||||
"桥墩(台)地面处拆模后": 30,
|
||||
"墩身混凝土施工": 30,
|
||||
"预制梁桥,预制梁架设前": 1,
|
||||
"预制梁桥,预制梁架设后": 7,
|
||||
"现浇梁,浇筑前": 30,
|
||||
"现浇梁上部结构施工中": 1,
|
||||
"架桥机(运梁车)通过": 2,
|
||||
"桥梁主体工程完工后,第1至3个月": 7,
|
||||
"桥梁主体工程完工后,第4至6个月": 14,
|
||||
"桥梁主体工程完工后,6个月以后": 30,
|
||||
"轨道铺设,前": 30,
|
||||
"轨道铺设,后": 14,
|
||||
"轨道铺设完成后,第1个月": 14,
|
||||
"轨道铺设完成后,2至3个月": 30,
|
||||
"轨道铺设完成后,4至12个月": 90,
|
||||
"轨道铺设完成后,12个月以后": 180,
|
||||
|
||||
# 桥梁旧工况
|
||||
"墩台施工到一定高度": 30,
|
||||
"墩台混凝土施工": 30,
|
||||
"预制梁桥,架梁前": 30,
|
||||
"桥位施工桥梁,制梁前": 30,
|
||||
"桥位施工桥梁,上部结构施工中": 1,
|
||||
"桥梁主体工程完工后,第1至3个月": 7,
|
||||
"桥梁主体工程完工后,第4至6个月": 14,
|
||||
"桥梁主体工程完工后,6个月以后": 30,
|
||||
"轨道铺设期间,前": 30,
|
||||
"轨道铺设期间,后": 14,
|
||||
|
||||
# 桥梁兼容变体
|
||||
"架桥机(运梁车) 首次通过前": 1,
|
||||
"架桥机(运梁车) 首次通过后,前3天": 1,
|
||||
"架桥机(运梁车) 首次通过后": 7,
|
||||
"预制梁桥预制梁架设后": 7,
|
||||
|
||||
# 隧道工况
|
||||
"仰拱(底板)施工完成后,第1个月": 7,
|
||||
"仰拱(底板)施工完成后,第2至3个月": 14,
|
||||
"仰拱(底板)施工完成后,3个月以后": 30,
|
||||
"无砟轨道铺设后,第1至3个月": 30,
|
||||
"无砟轨道铺设后,4至12个月": 90,
|
||||
"无砟轨道铺设后,12个月以后": 180,
|
||||
|
||||
# 隧道兼容变体(中文括号)
|
||||
"仰拱(底板)施工完成后,第1个月": 7,
|
||||
"仰拱(底板)施工完成后,第2至3个月": 14,
|
||||
"仰拱(底板)施工完成后,3个月以后": 30,
|
||||
|
||||
# 其他特殊工况
|
||||
"轨道板铺设前": 14,
|
||||
"站场填方路基段填筑完成至静态验收": 14,
|
||||
"特殊地段隧道施工完成后至静态验收": 14,
|
||||
"冬休": 0,
|
||||
}
|
||||
|
||||
# ==================== 旧→新等效映射(工况预测用) ====================
|
||||
OLD_TO_NEW_MAP = {
|
||||
# 路基等效
|
||||
"填筑或堆载,一般情况": "路基或预压土填筑,连续填筑",
|
||||
"填筑或堆载,两次填筑间隔时间较长情况": "路基或预压土填筑,两次填筑间隔时间较长",
|
||||
"堆载预压或路基填筑完成,第1至3个月": "预压土或路基填筑完成,第1~3个月",
|
||||
"堆载预压或路基填筑完成,第4至6个月": "预压土或路基填筑完成,第4~6个月",
|
||||
"堆载预压或路基填筑完成,6个月以后": "预压土或路基填筑完成,6个月以后",
|
||||
"轨道板(道床)铺设后,第1个月": "轨道板(道床)铺设后,第1至3个月",
|
||||
"轨道板(道床)铺设后,第2至3个月": "轨道板(道床)铺设后,第4至6个月",
|
||||
"轨道板(道床)铺设后,3个月以后": "轨道板(道床)铺设后,6个月以后",
|
||||
"铺路或堆载,一般情况": "路基或预压土填筑,连续填筑",
|
||||
"铺路或堆载,沉降量突变情况": "路基或预压土填筑,连续填筑",
|
||||
"铺路或堆载,两次铺路间隔时间较长情况": "路基或预压土填筑,两次填筑间隔时间较长",
|
||||
|
||||
# 桥梁等效
|
||||
"墩台施工到一定高度": "桥墩(台)地面处拆模后",
|
||||
"墩台混凝土施工": "墩身混凝土施工",
|
||||
"桥位施工桥梁,制梁前": "现浇梁,浇筑前",
|
||||
"桥位施工桥梁,上部结构施工中": "现浇梁上部结构施工中",
|
||||
"桥梁主体工程完工后,第1至3个月": "桥梁主体工程完工后,第1至3个月",
|
||||
"桥梁主体工程完工后,第4至6个月": "桥梁主体工程完工后,第4至6个月",
|
||||
"桥梁主体工程完工后,6个月以后": "桥梁主体工程完工后,6个月以后",
|
||||
"轨道铺设期间,前": "轨道铺设,前",
|
||||
"轨道铺设期间,后": "轨道铺设,后",
|
||||
"预制梁桥预制梁架设后": "预制梁桥,预制梁架设后",
|
||||
"架桥机(运梁车) 首次通过前": "架桥机(运梁车)首次通过前",
|
||||
"架桥机(运梁车) 首次通过后,前3天": "架桥机(运梁车)首次通过后,前3天",
|
||||
"架桥机(运梁车) 首次通过后": "架桥机(运梁车)首次通过后",
|
||||
}
|
||||
|
||||
# ==================== 工况分组(工况预测用) ====================
|
||||
CONDITION_GROUP = {
|
||||
# 路基分组
|
||||
"路基或预压土填筑,连续填筑": "DZ_CONTINUE",
|
||||
"路基或预压土填筑,两次填筑间隔时间较长": "DZ_INTERVAL",
|
||||
"预压土或路基填筑完成,第1~3个月": "DZ_FINISH_1_3",
|
||||
"预压土或路基填筑完成,第4~6个月": "DZ_FINISH_4_6",
|
||||
"预压土或路基填筑完成,6个月以后": "DZ_FINISH_AFTER_6",
|
||||
"架桥机(运梁车)首次通过前": "JQJ_FIRST_BEFORE",
|
||||
"架桥机(运梁车)首次通过后,前3天": "JQJ_FIRST_AFTER_3D",
|
||||
"架桥机(运梁车)首次通过后": "JQJ_FIRST_AFTER",
|
||||
"轨道板(道床)铺设后,第1至3个月": "GDB_FINISH_1_3",
|
||||
"轨道板(道床)铺设后,第4至6个月": "GDB_FINISH_4_6",
|
||||
"轨道板(道床)铺设后,6个月以后": "GDB_FINISH_AFTER_6",
|
||||
|
||||
# 路基旧工况分组
|
||||
"填筑或堆载,一般情况": "DZ_CONTINUE",
|
||||
"填筑或堆载,两次填筑间隔时间较长情况": "DZ_INTERVAL",
|
||||
"堆载预压或路基填筑完成,第1至3个月": "DZ_FINISH_1_3",
|
||||
"堆载预压或路基填筑完成,第4至6个月": "DZ_FINISH_4_6",
|
||||
"堆载预压或路基填筑完成,6个月以后": "DZ_FINISH_AFTER_6",
|
||||
"轨道板(道床)铺设后,第1个月": "GDB_FINISH_1_3",
|
||||
"轨道板(道床)铺设后,第2至3个月": "GDB_FINISH_4_6",
|
||||
"轨道板(道床)铺设后,3个月以后": "GDB_FINISH_AFTER_6",
|
||||
"铺路或堆载,一般情况": "DZ_CONTINUE",
|
||||
"铺路或堆载,沉降量突变情况": "DZ_CONTINUE",
|
||||
"铺路或堆载,两次铺路间隔时间较长情况": "DZ_INTERVAL",
|
||||
|
||||
# 桥梁分组
|
||||
"桥墩(台)地面处拆模后": "STATIC",
|
||||
"墩身混凝土施工": "STATIC",
|
||||
"预制梁桥,架梁前": "STATIC",
|
||||
"预制梁桥,预制梁架设前": "YZLQ_BEFORE_JS",
|
||||
"预制梁桥,预制梁架设后": "YZLQ_AFTER_JS",
|
||||
"现浇梁,浇筑前": "STATIC",
|
||||
"现浇梁上部结构施工中": "STATIC",
|
||||
"架桥机(运梁车)通过": "STATIC",
|
||||
"桥梁主体工程完工后,第1至3个月": "QL_ZHUTI_1_3",
|
||||
"桥梁主体工程完工后,第4至6个月": "QL_ZHUTI_4_6",
|
||||
"桥梁主体工程完工后,6个月以后": "QL_ZHUTI_AFTER_6",
|
||||
"轨道铺设,前": "STATIC",
|
||||
"轨道铺设,后": "STATIC",
|
||||
"轨道铺设完成后,第1个月": "GD_FINISH_1",
|
||||
"轨道铺设完成后,2至3个月": "GD_FINISH_2_3",
|
||||
"轨道铺设完成后,4至12个月": "GD_FINISH_4_12",
|
||||
"轨道铺设完成后,12个月以后": "GD_FINISH_AFTER_12",
|
||||
|
||||
# 桥梁旧工况分组
|
||||
"墩台施工到一定高度": "STATIC",
|
||||
"墩台混凝土施工": "STATIC",
|
||||
"桥位施工桥梁,制梁前": "STATIC",
|
||||
"桥位施工桥梁,上部结构施工中": "STATIC",
|
||||
"桥梁主体工程完工后,第1至3个月": "QL_ZHUTI_1_3",
|
||||
"桥梁主体工程完工后,第4至6个月": "QL_ZHUTI_4_6",
|
||||
"桥梁主体工程完工后,6个月以后": "QL_ZHUTI_AFTER_6",
|
||||
"轨道铺设期间,前": "STATIC",
|
||||
"轨道铺设期间,后": "STATIC",
|
||||
"预制梁桥预制梁架设后": "YZLQ_AFTER_JS",
|
||||
"架桥机(运梁车) 首次通过前": "JQJ_FIRST_BEFORE",
|
||||
"架桥机(运梁车) 首次通过后,前3天": "JQJ_FIRST_AFTER_3D",
|
||||
"架桥机(运梁车) 首次通过后": "JQJ_FIRST_AFTER",
|
||||
|
||||
# 隧道分组
|
||||
"仰拱(底板)施工完成后,第1个月": "YG_DIBAN_1",
|
||||
"仰拱(底板)施工完成后,第2至3个月": "YG_DIBAN_2_3",
|
||||
"仰拱(底板)施工完成后,3个月以后": "YG_DIBAN_AFTER_3",
|
||||
"无砟轨道铺设后,第1至3个月": "WZGD_1_3",
|
||||
"无砟轨道铺设后,4至12个月": "WZGD_4_12",
|
||||
"无砟轨道铺设后,12个月以后": "WZGD_AFTER_12",
|
||||
"仰拱(底板)施工完成后,第1个月": "YG_DIBAN_1",
|
||||
"仰拱(底板)施工完成后,第2至3个月": "YG_DIBAN_2_3",
|
||||
"仰拱(底板)施工完成后,3个月以后": "YG_DIBAN_AFTER_3",
|
||||
|
||||
# 其他特殊工况分组
|
||||
"轨道板铺设前": "STATIC",
|
||||
"站场填方路基段填筑完成至静态验收": "STATIC",
|
||||
"特殊地段隧道施工完成后至静态验收": "STATIC",
|
||||
|
||||
# 特殊工况
|
||||
"冬休": "STATIC",
|
||||
}
|
||||
|
||||
# ==================== 切换触发规则(工况预测用) ====================
|
||||
TRANSITION_RULES = {
|
||||
# 路基切换规则
|
||||
"DZ_FINISH_1_3": {"trigger_days": 90, "next": ["预压土或路基填筑完成,第4~6个月"]},
|
||||
"DZ_FINISH_4_6": {"trigger_days": 90, "next": ["预压土或路基填筑完成,6个月以后"]},
|
||||
"DZ_FINISH_AFTER_6": {"trigger_days": None, "next": None},
|
||||
"JQJ_FIRST_BEFORE": {"trigger_days": 1, "next": ["架桥机(运梁车)首次通过后,前3天"]},
|
||||
"JQJ_FIRST_AFTER_3D": {"trigger_days": 3, "next": ["架桥机(运梁车)首次通过后"]},
|
||||
"JQJ_FIRST_AFTER": {"trigger_days": None, "next": None},
|
||||
"GDB_FINISH_1_3": {"trigger_days": 30, "next": ["轨道板(道床)铺设后,第4至6个月"]},
|
||||
"GDB_FINISH_4_6": {"trigger_days": 30, "next": ["轨道板(道床)铺设后,6个月以后"]},
|
||||
"GDB_FINISH_AFTER_6": {"trigger_days": None, "next": None},
|
||||
|
||||
# 桥梁切换规则
|
||||
"YZLQ_BEFORE_JS": {"trigger_days": 1, "next": ["架桥机(运梁车)通过"]},
|
||||
"YZLQ_AFTER_JS": {"trigger_days": 7, "next": ["桥梁主体工程完工后,第1至3个月"]},
|
||||
"QL_ZHUTI_1_3": {"trigger_days": 90, "next": ["桥梁主体工程完工后,第4至6个月"]},
|
||||
"QL_ZHUTI_4_6": {"trigger_days": 90, "next": ["桥梁主体工程完工后,6个月以后"]},
|
||||
"QL_ZHUTI_AFTER_6": {"trigger_days": None, "next": None},
|
||||
"GD_FINISH_1": {"trigger_days": 30, "next": ["轨道铺设完成后,2至3个月"]},
|
||||
"GD_FINISH_2_3": {"trigger_days": 60, "next": ["轨道铺设完成后,4至12个月"]},
|
||||
"GD_FINISH_4_12": {"trigger_days": 240, "next": ["轨道铺设完成后,12个月以后"]},
|
||||
"GD_FINISH_AFTER_12": {"trigger_days": None, "next": None},
|
||||
|
||||
# 隧道切换规则
|
||||
"YG_DIBAN_1": {"trigger_days": 30, "next": ["仰拱(底板)施工完成后,第2至3个月"]},
|
||||
"YG_DIBAN_2_3": {"trigger_days": 60, "next": ["仰拱(底板)施工完成后,3个月以后"]},
|
||||
"YG_DIBAN_AFTER_3": {"trigger_days": None, "next": None},
|
||||
"WZGD_1_3": {"trigger_days": 90, "next": ["无砟轨道铺设后,4至12个月"]},
|
||||
"WZGD_4_12": {"trigger_days": 240, "next": ["无砟轨道铺设后,12个月以后"]},
|
||||
"WZGD_AFTER_12": {"trigger_days": None, "next": None},
|
||||
|
||||
# 静态分组(无切换)
|
||||
"DZ_CONTINUE": {"trigger_days": None, "next": None},
|
||||
"DZ_INTERVAL": {"trigger_days": None, "next": None},
|
||||
"STATIC": {"trigger_days": None, "next": None},
|
||||
}
|
||||
|
||||
# ==================== 冬休标识 ====================
|
||||
WINTER_BREAK_LABELS = {"冬休"}
|
||||
Reference in New Issue
Block a user